November 12, 2026
By the project's own schedule, the highway through Wilson should look mostly the way it did before construction by the time winter settles in. The plan is for crews to take the cones and barricades off WY-22 and to repave the travel lanes to full width and restripe them before the winter pause. According to Buckrail's Nov. 6 report, the lane count will be "generally similar" to before construction started. The new curb along the north side and the pathway grade behind it are the clearest signs of what happened in town since July.
That's how the season was planned. Most of the money and effort in 2026 went into things you can't see from the driver's seat. Wilson spent two years arguing over the center turn lane, the pathways, the bus pullouts, the crosswalk and the lighting. The turn lane is pushed to summer 2027, the south-side pathway comes after the north side is finished, and commissioners still have the lighting question in front of them.
Work started in late July. Buckrail reported on July 17 that construction would begin "on Monday," with crews working weekdays from 7 a.m. to 7 p.m. That start came about two weeks after the tentative July 6 date in the project's June 22 press release.
Since then, all of the work has been on the north side of the highway. By early November, the Teton BUILD Grant team reported these pieces complete:
The project's November release, as quoted by Buckrail, set one priority for the last weeks of the season: "to ensure the roadway and vehicle entrances are fully paved and ready for winter travel." Paving the north-side pathway came second, "if time and weather permit." Any pathway that doesn't get paved before the snow stays as graded gravel until crews come back.
When the contract was signed in May, it called for substantial completion by Nov. 20, 2026, and final completion by Dec. 23, 2026. That schedule no longer applies. No work is planned this winter, and construction is expected to start again in April 2027.
The plan commissioners approved was meant to change how people use the stretch past Hungry Jack's General Store, Fish Creek Center, Nora's Fish Creek Inn and the Stagecoach Bar. It called for two through lanes plus a center lane so drivers could turn into local businesses without holding up Teton Pass traffic. It also added pathways about 10 feet wide on both sides of the road, set behind a buffer. This is where each of those pieces stands for the winter:
| Feature | Where it stands this winter |
|---|---|
| Center turn lane through downtown | The extended three-lane section moves to summer 2027 |
| North-side pathway | Paving if time and weather allowed, with any unpaved sections left as graded gravel |
| South-side pathway and curb work | Starts after the north side is finished |
| Bus turnouts at Hungry Jack's and Fish Creek Center | Approved in 2025, with adjustments expected after Hungry Jack's declined an easement |
| Push-button flashing-beacon crosswalk near West Street and Fall Creek Road | Part of the approved plan |
| Street lights | Commissioners asked for safety data and a look at solar options in June 2026 |
The lighting question goes back further than this year. Teton County Pathways Coordinator Brian Schilling told commissioners that officials had considered street lights before and decided against them because of concerns about community character, the Jackson Hole News&Guide reported. At the June meeting he said, "There are real safety benefits to having lighting." Commissioners told staff not to let the lighting review hold up construction. Schilling said any lights would have to be dark-sky compliant and point downward. Solar fixtures came up because they wouldn't require running power lines underground.
The roadside buffer will look plainer than early drawings showed. The design options report called for native grasses between the path and the road and considered irrigation conduit and trees. A May 2026 change order took out the conduit and the trenching for it, citing cost, WYDOT limits on landscaping, and concern about drawing wildlife toward the highway.
Commissioners approved the Wilson Active Transportation Improvements Project 4–0 on Jan. 7, 2025. The hearing took up most of a day. Nearly 30 people commented, and Commissioner Natalia D. Macker had left before the vote. The approval came with changes. The board dropped a north-side pathway segment east of Fish Creek and favored sloped ground over retaining walls in the contested spots. It also asked staff to keep parking where possible, called for stamped, colored asphalt and some concrete instead of plain black asphalt, and kept the bus pullouts in the plan.
The retaining walls drew the most attention at the meeting. Several commenters said walls between the pathways and business parking lots would block moose and other wildlife moving through town. Buckrail reported that commissioners then voted unanimously to drop the retaining-wall option and plan for sloped ground instead. The finished work list for 2026 still includes a retaining wall north of Edmiston Springs, along with other walls in the contract's scope.
The debate continued after the vote. Opponents formally organized on May 28 as a political action committee called Concerned Citizens of Wilson and raised concerns about safety and wildlife. The Wilson Advocacy Group continued to back the project, the News&Guide reported.
The funding explains part of the pace. Evans Construction's bid of $5,000,625 came in above the engineer's estimate of $4,103,126. A $285,301 change order cut the contract to a not-to-exceed amount of $4,715,324. The project carries the BUILD grant name, but only $698,441 of the construction money comes from BUILD. A federal TAP grant pays $1,249,999, and the local share is $2,766,884, about 59 percent of the contract. For comparison, the regional Teton Mobility Corridor Improvements program received $25 million in federal BUILD awards in 2020 and 2022, spread across all of its projects.
The Wilson corridor's winter pause lines up with several other seasonal closures and cutbacks around it:
With the park road closed until spring, WY-22 is the main paved way in and out of Wilson. Pass traffic and local errands will share the newly striped downtown lanes all winter, and the center turn lane is still to come.
Crews are expected back in April 2027, weather permitting. They'll finish the north side first and then move to the south side to build the same kind of improvements there. The extended three-lane section is scheduled for next summer. When the work is done, the county's contract describes about 2,100 linear feet of multi-use pathway on both sides of WY-22 through downtown Wilson. The contract also includes wider shoulders, stormwater collection and treatment, a rapid-flashing beacon, retaining walls, and new signs and striping.
If you own property along the WY-22 corridor and want to know how the finished design could affect your driveway, frontage or value in 2027, The McPeak Group is following the project closely. Request a Home Valuation, and we'll go over what the next two construction seasons mean for your piece of Wilson.
November 19, 2026
November 12, 2026
November 5, 2026
October 29, 2026
October 22, 2026
October 15, 2026
October 8, 2026
October 1, 2026
September 24, 2026
We’ve cut our teeth helping our friends with first-time home purchases in a rapidly changing market. Those friends have come back repeatedly as their needs have changed for larger homes or investment properties. We’re always looking to help new friends and introduce them to the valley and lifestyle we’ve come to love.